|
2000
- NEW
SUPREME COURT
Diaphragm Wall |
|
Works Equipment The diaphragm wall for the New Supreme Court was constructed between June 2000 and September 2000. In the centre of Singapore the diaphragm wall was an advanced works contract awarded directly to Bachy Soletanche by the Supreme Court of the Government of Singapore. The Client's Engineer PWD design for the basement enclosed the existing basement remaining from the demolition of Columbo Court, which previously occupied part of the site. The site consisted of 10,000m2 of 1000mm
thick diaphragm wall up to 35m deep. Two hydraulic grabs, KS 3000,
were used to complete the excavation works well within programme.
The ground conditions varied accross the site but were essentially
fill and sand for the initial 5m overlaying 5m to 17m of soft marine
clay and then dense old alluvium. Note that both machines are working on the
temporary decking. |