2000
- TRENT
ENGINE FACILITY, CALSHOT ROAD
Diaphragm Wall & Extractable Ground Anchors |
|
Client: Singapore Aero Engine Services Pte
Ltd (SIA-Rolls Royce) Diaphragm Wall:
4,700m2, 0.6m-1.2m thick, 32m deep A retaining wall at the new Trent Engine Overhaul Facility at Changi. The retaining wall is formed with T panels and had two layers of temporary (removable) ground anchors. The diaphragm wall was executed from a raised working platform with a steep access and limited working room. Despite the very tight diaphragm wall programme, 12 weeks overall including mobilisation, the project finished 1 week ahead off schedule allowing the Main Contractor early access to the site. The project was carried out using a conventional diaphragm wall grab 'KL' with a short spell with the hydraulic 'KS' machine to boost production at a critical phase of the work. |